Project Balance Check - Project Monthly Amounts are not being updated using Mass Period Change in Month End Manager

Description of Issue

Project Month Amounts are not being updated using Mass Period Change in Month End Manager

Context
  • Month End Manager (MEM)
  • Change Period
  • Project Balance Check (pabalchk)
Cause

Work ticket MUN-380732 is open with development to address Mass Change Period in Month End Manager are not updating Project Monthly Amounts

Resolution

Project Balance Check will pick up on this error but it will take support to process the update