Requisitions program ignores available budget check at Major Project level
Description of Issue
- User does not have permission to override budget and enters a requisition in Requisitions .NET program
- Include in budget check has been checked on expense string
- Major project has available budget and project does not
- Major project has been defined on subordinate project in Project Master
- Budget level is set to Major Project in Project Master
Context
Project Master
Requisitions
Requisition Entry
Cause
Requisitions program ignores available budget check at Major Project level
Resolution
- Install work ticket MUN-328093 when it becomes available
- Use Requisition Entry as a temporary solution
Additional Information