Description of Issue
  • User does not have permission to override budget and enters a requisition in Requisitions .NET program
  • Include in budget check has been checked on expense string
  • Major project has available budget and project does not
  • Major project has been defined on subordinate project in Project Master
  • Budget level is set to Major Project in Project Master
Context

Project Master

Requisitions

Requisition Entry

Cause

Requisitions program ignores available budget check at Major Project level

Resolution
  • Install work ticket MUN-328093 when it becomes available
  • Use Requisition Entry as a temporary solution