Description of Issue

When scheduling a job the notify option when job completes, include document link(s) is not listed as an option.



Context
  • Scheduler Administration

  • Tyler Content Manager

  • Reports



Cause

The Content Management System setting is set to None.



Resolution
  1. In the Tyler Menu navigate to TylerCM for Munis settings.

    • System Administration > General Administration > TylerCM for Munis Settings

  2.  Review the field Content Management System and determine if this is set to the value None.



Additional Information

The include document link option is only available with use of Tyler Content Manager.

If you don't currently own Tyler Content Manager you would need to speak to your sales representative.

If you own Tyler Content Manager and need this setting updated you will want to reach out to the Munis Server support teams (TSM On Prem or TSM SaaS)