Next Year Budget Report does not show all funds
Description of Issue
Ran Next Year Budget Report for all Funds but not all funds returned results on report.
Context
Next Year Budget Report
Next Year Budget Entry
Define/Start Budget Projection
Cause
Next Year Budget Report will only show the Funds that exist on the projection the report is being run for.
Resolution
Go to Financials > Budget Processing > Next Year Budget Entry
Enter Projection number of the projection you are using for the report.
Click Accept
Click Accept
Look to see if missing funds exist on this projection.Â
If Funds do not exist on the projection they won't show on the report.