Error selecting budget amount on level x when exporting a project budget package to the GL



Description of Issue

When exporting a project budget package to the GL budget projection the following error is received:

Error selecting budget amount on level x -284 ISAM -1

Additional information concerning a status error of -284:
A subquery has returned not exactly one row.

If you have any questions, please contact Munis Technical Support

System log Id:xxxxxx



Context

Project Budget Package

Export to GL



Cause

The error persists when exporting a project budget package more than once to the same GL budget projection



Resolution

Work ticket MUN-440873 is open with development to address the issue

Please contact Munis General Ledger Support for further assistance



Additional Information

When the error is received a detail record is still generated without the project string and will have Non-project related amount defined in the description field