Cannot Change Projection Number in Next Year Budget Entry or Central Budget Entry
Unable to change the projection number in Next Year Budget Entry or Central Budget Entry
Can't access a budget projection number. Only one projection is available for the user to view.Â
Next Year Budget Entry
Central Budget Entry
If a user has Budget permissions set for Maximum Budget Level of 1, they will only be able to view the Default Operational Projection set in Budget Settings
There are two options to resolve this:
Financials > Budget Processing > Budget Settings
Update the settings and change the Default Operational Budget Projection to be the projection number they currently need access to (this will update for all users).
or
System Administration > Security > User Attributes
Search for the User Id
Select a role that grants Budgeting permissions- click Edit Role (impacts all users in role)
Select the Budget folder and Update
Change the Maximum Budget Level to a value higher than 1
Â