Description of Issue
  • Unable to update on Funding Source Strings in Project Master, but can update on Expense Strings
  • User has permission to "Maintain Project Strings"
Context

Project Master

Resolution

To resolve, the user's Project Account permissions will need to be updated.

System Administration > Security > User Attributes

  1. Search for the User Id
  2. Highlight the Role that grants Project Accounting permissions and select Edit Role
  3. Select the Project Accounting Folder
  4. Update and select the checkbox for "Maintain revenue allocation setup"

Please note: Updating a Role impacts all users assigned to that Role.

Cause

Missing Project Accounting permission to "Maintain revenue allocation setup"