Description of Issue
  • Clicking update and save without changing any fields updates the Modified date

  • Modified date doesn't match the audits listed within View Changes



Context

Project Master

Project Expense String

Project Funding Source



Cause

User clicked Update and Accept without making any changes



Resolution
  • Modified will reflect the last time that the Accept option as clicked from Update mode. If update is cancelled the modified field will not be updated. 

  • The View Changes option will reflect field changes, if no changes are made there will be no record generated.