'Journal total is greater than the available budget 0.00 for project string xxxxx-xxxxxx' - PL string not flagged to be included in Budget check



Description of Issue

'Journal total is greater than the available budget for string' budget check warning when using a project string that is not flagged to be included in the budget check

PL string not flagged to be included in the budget check. BUA created that reduces the available budget (but does not go over budget), the invalid available budget message above occurs

Context

Budget Transfers and Amendment

Project String

Cause

Resolution
  • Work ticket MUN-254749 is open with Development to resolve the invalid available budget message
  • Accounting Entries can be used to complete the Budget amendment : Financials > General Ledger Menu > Journal Entry/History
Additional Information