Unable to allocate to any project strings in the Requisitions program



Description of Issue

While entering a requisition in the Requisitions program, during allocation, the project string fields are visible, but when clicking into the field, it disappears.



Context
  • Munis

  • Purchasing

  • Requisitions



Cause

This is a Munis defect.



Resolution
  • Use of the Requisition Entry program as an alternative : Munis > Financials > Purchasing > Purchase Order Processing > Requisition Entry

  • Install MUN-427746 from MIU when available.



Additional Information

If a user has multiple project ledger data accesses setup, the Requisitions program will treat the permissions as exclusive, as opposed to inclusive.