Year End Manager checklist task incorrectly marked as Complete
Accidentally marked tasks from a Year End Manager checklist as 'Complete'
Can we reverse the 'Complete' status of a Year End Manager task?Â
Year End ManagerÂ
Checklist
Status
Once a task has been marked as 'Complete' this field receives a timestamp, is grayed out, and can no longer be updated
Remove the task from the checklist, and then re-add it back in.Â
NOTE: Before proceeding, it's recommended to take a screenshot of the existing task to capture information (if it was defined), such as the Due Date, Assigned to, Reminder date, and any comments left on the task. Also make note of which position(s) in the list the tasks were assigned
Navigate to Year End Manager: Financials > General Ledger Menu > End of Period > Fiscal Year End Processing > Year End ManagerÂ
Select the checklist from the year dropdown
Edit Checklist from the ribbon
Select the checkboxes next to any task that was improperly set to 'Completed' status
'Remove from checklist' link that should now appear towards the top right of the screen
Depending on whether the removed tasks are System Generated, or User Defined, you will now see those tasks listed on the left side of the screen under the appropriate tab
Select the checkboxes next to any task on the left side of the screen you want to add back to the checklist
'Add to checklist' link that should now appear on screen
Any selected task will now be added to the checklist on the right side of the screen, but they will be listed as the last item(s) on the list
Locate newly added task, hover mouse over them to get the four-way arrow cursor
Drag and drop tasks back to their original position
Return option from ribbon
Re-added tasks will now appear in your checklist and have a 'Not Started' status. The Due Date, Assigned to, Reminder date, Comments, etc. fields will need to be redefined