PM work orders did not generate - Due to Use Department Calendar checkbox
Description of Issue
PM work orders did not generate
Context
Tyler EAM
Cause
PM detail on asset had the Use Department Calendar checkbox enabled, but the servicing department was missing a defined calendar for that year
Resolution
- Uncheck the Use Department Calendar checkbox, or
- Add a defined calendar for the servicing department
Additional Information