Life to date project strings revised budget is not exporting correctly when multiple project available budget types exist in the find set

Description of Issue

The revised budget for next year is not exporting to excel correctly for life to date project strings

Context

Project Ledger

Expense string Inquiry

Funding Source Inquiry

Excel Export

Cause

When exporting a mix of yearly and life to date projects, when a Yearly project string is first in the find set the revised budget for next year does not export correctly for life to date project strings

Resolution

Work ticket MUN-419074 is open with development to address the issue

As a work around you can define your find set by the projects available budget - once for Life to date and then again for Yearly

Additional Information

When this occurs, the revised budget that carries forward automatically from the current year is being excluded

This impacts the Revised Budget and the Available budget for future years