Pick Ticket Requisition converted different month updating Project Ledger incorrectly
Description of Issue
Pick ticket requisitions entered in one month then converted in another month do not update Project Ledger monthly amounts correctly
Context
- Project Balance Check (pabalchk)
- Requisitions
- Pick Tickets
Cause
When a pick ticket requisition is created in one month, then converted into a pick ticket in another month, one the pick ticket is issued.
The project string monthly amount updates the incorrect month.
Resolution
- Contact Munis Financial General Ledger Support to log a case and have these items reviewed
- Support will tie to known work ticket if relevant open with development MUN-242213
- There is no known work around for this issue.