Description of Issue
When creating a Project in the Project Master program, the following error occurs:
Project's available budget must be the same as its Major Project.
Context
Project Ledger
Project Master
Cause
This error occurs if this Project's 'Project available budget' setting is not the same as it is on its Major Project.
Resolution
To correct this Project's available budget setting and resolve this error:
- Take note of what this Project's 'Major project' setting is on the Project Master screen
- Click Search
- In the 'Project' field, enter that Major Project code
- Click Accept
- Take note of what this Project's 'Project available budget' setting is
- Click Search
- Bring up your original Project again where you were receiving this error
- Click Accept
- Click Update
- Update the 'Project available budget' setting to the one of the Major Project
- Click Accept
Additional Information
, multiple selections available,
Related content
Journal total is greater than the available budget XXXX for project string XXXX-XXXX error on a transaction - Budget Level setting is incorrect
Journal total is greater than the available budget XXXX for project string XXXX-XXXX error on a transaction - Budget Level setting is incorrect
More like this
Project Budget Adjustment Entry error - This account cannot be used
Project Budget Adjustment Entry error - This account cannot be used
More like this
Unable to update Project Fiscal Range when Adding Project - Missing Project Accounting 'Allow Project Fiscal Range Override' Permission
Unable to update Project Fiscal Range when Adding Project - Missing Project Accounting 'Allow Project Fiscal Range Override' Permission
More like this
No records were found that satisfy the selection criteria - Revenue Allocation - Expense Type blank or incorrect on Project Expense String
No records were found that satisfy the selection criteria - Revenue Allocation - Expense Type blank or incorrect on Project Expense String
More like this
No records were found that satisfy the selection criteria - Project Revenue Allocation - Project Type was not defined in Project Master
No records were found that satisfy the selection criteria - Project Revenue Allocation - Project Type was not defined in Project Master
More like this
Project Budget Package Entry- Error Selecting project's fiscal year
Project Budget Package Entry- Error Selecting project's fiscal year
More like this