Rolling Budget - Keep Higher Level Amounts Intact
Rolling Budget - Keep Higher Level Amounts Intact
Description of Issue
Updates were made in Level 3 but need Level 2 amounts rolled forward
Context
- Budget Projection
- Next Year Budget Entry
- Next Year Budget Reports
- Post to Master for Reports
Cause
Client made updates in higher level before rolling the working budget level to that higher level.
Resolution
Select Keep when rolling the budget. This will move amounts from the lower level up, while "keeping" updates made in the higher level intact.
Munis > Financials > Budget Processing > Roll/Factor/Merge Projection
See Connect 2022 Budget Preparation - Best practices throughout your budget process for specific program procedures.
Additional Information
, multiple selections available,
Related content
Rolling Lower Level Budget Amounts to Higher Level Overwriting Amounts at Higher Budget Level
Rolling Lower Level Budget Amounts to Higher Level Overwriting Amounts at Higher Budget Level
More like this
User is unable to enter an amount in a level not showing in Central Budget Entry
User is unable to enter an amount in a level not showing in Central Budget Entry
More like this
Amounts not being copied when copying a budget projection
Amounts not being copied when copying a budget projection
More like this
MASTER IS COMPLETE: Budget already established for XXXX year not updated in budget settings
MASTER IS COMPLETE: Budget already established for XXXX year not updated in budget settings
More like this
Budget Projection amounts are not showing on reports
Budget Projection amounts are not showing on reports
More like this
How to copy a Budget Projection
How to copy a Budget Projection
More like this