Amounts not being copied when copying a budget projection
Amounts not being copied when copying a budget projection
Description of Issue
Copied a budget projection but the new projection does not have any amounts while the original does
Context
Define/Start Budget Projection
Next Year Budget Entry
Central Budget Entry
Cause
Original projection is not rolled to the highest budget level and the 'Copy max. budget level' option was selected
Resolution
Unselect the 'Copy max. budget level' option when copying the projection
or
Roll the original projection amounts to the highest level:
Enterprise ERP > Financials > Budget Processing > Roll/Factor/Merge Projection
Click Search
Enter projection number
Click Accept
Click Roll/Factor
Click Search
Click Accept
Click Roll/Factor
Select necessary options
Click Accept
Click Yes
Additional Information
Related content
How to copy budget detail from a posted budget projection into a new projection
How to copy budget detail from a posted budget projection into a new projection
More like this
Projected Actuals is not correct when copying a projection
Projected Actuals is not correct when copying a projection
More like this
How to copy a budget projection and not bring in amounts
How to copy a budget projection and not bring in amounts
More like this
How to copy a Budget Projection
How to copy a Budget Projection
More like this
Projected amount does not sum to account after copying the projection
Projected amount does not sum to account after copying the projection
More like this
Copy max budget level only moves values for NY1 and NY2 from Max level to first level in new projection
Copy max budget level only moves values for NY1 and NY2 from Max level to first level in new projection
More like this