Projected Actuals Column Not Showing in Central Budget Entry
Description of Issue
Why does Next Year Budget Entry allow entry of Projected Actuals when Central Budget Entry does not?
Context
Central Budget Entry
Cause
Projected Actuals was not checked in Account Columns
Resolution
To make Projected Actuals column display in Central Budget Entry:
1. Click Account Columns in the ribbon
2. Click Projected Actuals check box
3. Ok
Additional Information
- Projected Actuals can also be updated at the detail level
- Changes made to Account Columns follow individual users