Long Account Excel Budget Import Does Not Overwrite Existing Accounts With Zero Dollar Amounts

Description of Issue
  • Importing using Excel Budget Import format for long accounts does not overwrite existing accounts in projection when zero dollars are in the import template
  • Client is importing into an existing projection
Context
  • Define/Start Budget Projection
  • Next Year Budget Entry
  • Central Budget Entry
  • Budget Projection Import Templates
Cause


Resolution
  • MUN-331343 is currently open with Development to allow existing account amounts to be overwritten to 0.00 in a budget projection when the Excel Budget Import is used.
  • The current work around would be to use the standard long account import format - This format cannot be used to update detail amounts in a projection.
Additional Information

Zero dollar amounts imports for accounts that were not previously in the projection