Budget Completion Journal - Projection must be active

Budget Completion Journal - Projection must be active

Description of Issue

When defining Budget Completion Journal for projection number error display in red at bottom of screen
Projection must be active

Context
  • Budget Completion Journal
  • Error Message
  • Status
  • 2019.1 and above
Cause
  • Only Budget Projections that have a status of Active in Define Start Budget Projection can be output posted which then changes status to Posted
  • Starting in version 2019.1 and in all versions higher budget projections now have a status





Related content

Budget Projection Status needs to be Updated to Posted or Outdated
Budget Projection Status needs to be Updated to Posted or Outdated
More like this
Budget Completion Journal error- Open New Fiscal Year program has not been run
Budget Completion Journal error- Open New Fiscal Year program has not been run
More like this
Budget Completion Journal Error - The journal year is not valid
Budget Completion Journal Error - The journal year is not valid
More like this
Define Start Budget - updates are not allowed on posted projections error occurs when trying to master a projection
Define Start Budget - updates are not allowed on posted projections error occurs when trying to master a projection
More like this
All budget amounts in the projection are zero - Budget Completion Journal Update cannot be posted
All budget amounts in the projection are zero - Budget Completion Journal Update cannot be posted
More like this
Budget projection status shows as posted when the projection had not yet been posted
Budget projection status shows as posted when the projection had not yet been posted
More like this