Enterprise ERP Testing Timelines

Enterprise ERP Testing Timelines



Description of Issue

Overview on Testing an in-place upgrade versus a server migration.  Why on Server Transfers testing, why will it take max 6+ months as opposed to 12 weeks with in-place? Which document speaks to the additional Server Transfers testing? Is there a Server Migration documentation from the testing perspective?



Context
  • In-Place Upgrade

  • Server Migration



Cause

Informational.



Resolution

Testing for in-place upgrades on existing servers usually takes 8 - 12 weeks.  When upgrading in place, you are reviewing the operation with your business practices.

Testing for server migrations usually takes anywhere from 12 weeks to six months.  When you add new infrastructure into the mix, you have other hardware (printer, scanners, etc.), connectivity to other devices or resources at your site, as well as tuning the system.



Additional Information












Related content

Enterprise ERP Upgrade Timeline
Enterprise ERP Upgrade Timeline
More like this
Suggested testing time lengths for EERP upgrades
Suggested testing time lengths for EERP upgrades
More like this
In-place vs Server Transfer Migration
In-place vs Server Transfer Migration
More like this
What is the timeline for an in-place upgrade
What is the timeline for an in-place upgrade
More like this
Enterprise ERP Upgrade Configuration Guide
Enterprise ERP Upgrade Configuration Guide
More like this
Upgrading EPL or EERP when you own both
Upgrading EPL or EERP when you own both
More like this