Description of Issue

The Weekly Summary Report in ExecuTime seems to be missing some entries of hours. 

Example: In the Time Card Inquiry for pay period 07/16/2018 - 08/15/2018 it will calculate the days from 716-7/20 adding up to 39.75. But if you go to the pay period 06/16/2018 - 07/15/2018, it did not calculate the 1.00 hour on 7/14/2018

Context
  • ExecuTime 
  • Weekly Summary Report
Cause

Known Defect. 

Resolution

This will be corrected in work ticket XTSP-306 included in Service Pack 2021.3.