Description of Issue

Total Budget Amount does not represent the project year detail amounts.

Why is there a difference between project detail amount and total budget amount?

Context
  • Project Budget Package Entry

  • Project Budget Package Post (PAB)

  • Configuration & Setup

Cause

Total Budget Amount is the total of all project years in the project budget package for that project string, all hard amounts and all amounts summed by detail.

Resolution

Use the Detail amount range arrows to display the needed budget year detail amounts on the project strings section.

Additional Information
  • When using Project Budget Package Post ensure you correctly define the Post option:

    • Total package amounts will post the Total Budget Amount in Project Budget Package Entry

    • Package detail year only will post only defined detail year amounts in Project Budget Package Entry









Related content

Projected value for Account shows as 0.00 when detail with projected amounts exist and Sum detail projected to account level is checked
Projected value for Account shows as 0.00 when detail with projected amounts exist and Sum detail projected to account level is checked
More like this
Project Budget Package posting to incorrect Project Year - Different Project Fiscal Ranges
Project Budget Package posting to incorrect Project Year - Different Project Fiscal Ranges
More like this
Project Detail History Report - Available Budget does not match Project Expense Inquiry
Project Detail History Report - Available Budget does not match Project Expense Inquiry
More like this
The projected actuals are wrong in my projection when including budget detail
The projected actuals are wrong in my projection when including budget detail
More like this
Project Budget Report shows incorrect amounts when running for multiple projects
Project Budget Report shows incorrect amounts when running for multiple projects
More like this
Projection Totals tab does not display budget detail amounts for Revenue accounts
Projection Totals tab does not display budget detail amounts for Revenue accounts
More like this