Description of Issue
- I am upgrading our Munis version. Do I need to develop an internal project plan?
- We are upgrading from 11.3 to 2021.1, do we need to setup our own plan?
Context
- Munis
- Upgrade
- Project Management Plan
Cause
Unsure if an internal project plan is necessary for their upgrade the new version
Resolution
- A project plan that includes change management for key stakeholders is highly recommended
- Please review our sample Munis Upgrade Project Plan
- Tyler Community > Upgrade Resource Center > Planning > Munis Upgrade Project Plan
Additional Information
0 Comments