Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleDescription of Issue
  • Users receive Access Denied on Budget Completion Journal
  • Why am I unable to open the Budget Completion Journal?
  • Permission error encountered when opening Budget Completion Journal/Update program

Munis (bgcmpjnl) Permission denied for this application

  • User has full budget permissions 

...

Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleContext
  • Budget Completion Journal/Update
  • Permissions
  • Max Budget Level
  • Upgrade to Munis 2018.1 or higher

...

Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleCause
  • User has one or more Roles assigned where the Budget module permission Maximum budget level is blank. Munis is reading this blank value as NULL.
  • A slight change in the Maximum budget level permission field causes it to revert to null when upgrading from 2017.3 or below to 2018.1 and above if the highest budget level defined in GL settings was below 5 during the upgrade. In the former versions, the maximum budget value only had 5 levels available, despite the max budget level defined in General Ledger Settings, in 2018.1 the maximum level noted in GL Settings becomes the highest available within the Budget section of a users role. 


Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleResolution

Update all Roles with Budget module permissions to at least level 1 super user who needs budget completion journal must have max level equal to final budget level defined

Updating a Role impacts all users assigned to the Role

  1. Browse to System
Administration 
  1. Administration > Security > User Attributes 
  2. Click Search
  3. Enter [user information] to search
  4. Accept
  5. Left-click relevant role
  6. Edit role
  7. Budget folder
  8. Update
  9. Maximum budget level dropdown
  10. Select 1 from the dropdown
    • Super user who needs budget completion journal must have max level equal to final budget level defined
  11. Accept

User should reopenBudget Completion/Update Journal program

...