Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleContext
  • Define Start Budget Projection
  • Roll Factor Merge Projection
  • Next Year Budget Entry
  • Central Budget Entry


Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleCause

During Budget Projection Import the Projection number to use was manually added as 0

or 

During the Merge process two projections are merged into one with the number 0


Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleResolution

If this was from an Import:

Reimport the budget projection and assign a new number

If this is from a Merge:

Redo the merge giving the new projection a number other than 0

Work ticket MUN-439479 was created to address this issue

For both instances the 0 projection will not be able to be deleted until the MUN is released as it will also address the 0 projections not showing within Define/Start Budget Projections.  


Panel
borderColor#03396c
titleColorWhite
titleBGColor#03396c
titleAdditional Information


...